Construction Update – January 4, 2010

January 4th, 2010
The loading rack is taking shape.

The loading rack is taking shape.

Replacing some ties on the track.

Replacing some ties on the track.

More rail maintenance getting done before the first rail cars arrive.

More rail maintenance getting done before the first rail cars arrive.

The control room taking shape.

The control room is almost ready.

Construction Update – December 9, 2009

December 9th, 2009
Truck scale installation.

Truck scale installation.

Installing an air cooler.

Installing an air cooler.

Things are getting crowded.

Things are getting crowded.

Looking NW toward the plant.

Looking NW toward the plant.

Construction Update – December 4, 2009

December 4th, 2009
Diesel tank.

Diesel tank.

Some of the last pieces of equipment to arrive.

Some of the last pieces of equipment to arrive.

The truck loading rack under construction.

The truck loading rack under construction.

The LPG bullet and piping.

The LPG bullet and piping.

Installing insulation on the de-ethanizer.

Installing insulation on the de-ethanizer.

Concrete work for the truck scale.

Concrete work for the truck scale.

Raw material tanks.

Raw material tanks.

We’re almost there!

November 30th, 2009

You know we’re getting close to being done when the logo is painted on the finished diesel tank!!

Finished diesel tank.

Finished diesel tank.

Construction Update – November 30, 2009

November 30th, 2009
Fractionator being lowered into place.

Fractionator being lowered into place.

Finishing insulation on the debutanizer.

Finishing insulation on the debutanizer.

Forming up the finished product loading area.

Forming up the finished product loading area.

Truck loading area foundations.

Truck loading area foundations.

Forming up the truck scale.

Forming up the truck scale.