April 12th, 2010
Weather has been warm and dry, “Good” construction weather.

Heat Exchanger Piping Insulation Being Insulated.

Rail Unloading Area.

Pipe Rack Getting Pretty Full And Other Piping Being Insulated.

Core Reactor Area Progressing.

Looking Toward The Plant From Out By The Flare Area.

Truck Loading Area Being Graded.
March 8th, 2010
Construction crews worked through the weekend to take advantage of the cool dry days.

Feed reception and storage tanks.

Tarps are used to block the wind for welders installing pipe.

North Process Area

West Process Area

South Process Area

North Process Area.

Truck Loading Station for Products.
February 9th, 2010
While much of the country seems to be covered in snow, we continue to work on finishing the plant. These pictures are also proof that not everyone in Louisiana is in New Orleans celebrating the Saints’ victory…..

Sunrise at the plant.

A beautiful day to work on piping.

Working on finishing the piping.

Welding on pipes.

One of the last pieces of equipment being put in place.