All plant systems have been turned over to our Operations and Maintenance groups from the Project Team for commissioning and start up. We are in the commissioning process, including the flushing of lines, confirming control system functionality, inventorying the systems, and loading absorbents and catalysts. Here are some recent pictures from the plant.

Loading the absorber system.

Hot oil system is being commissioned.

Hydrogen compression construction completed.

Process heat exchangers getting final insulation installed.

Reactor area looks better with all the scaffold removed.

Fractionation towers ready to go to work.